Recently Completed

Antioch High School

This project includes a 20 classroom addition to Antioch High School.  This project will allow the classes currently in portable buildings on the campus to be moved inside the building. 

Antioch High School

Project details

Mayor
Megan Barry
Council
District 32 - Jacobia Dowell email
School board
District 6 - Tyese Hunter email
Location
1900 Hobson Pike map it
Total project square footage
39,825 SF
Allocated funding
$6,900,000
Architect
JJCA
Contractor
TBD
Anticipated completion date
June 2018

Construction Updates

Updates will be posted on a monthly basis while the project is under construction.


Update: (08-01-2018)

The addition at Antioch High School is complete.


Update: (07-01-2018) 

2018-07-01.jpg

Building A:  Complete except for cleaning and correcting punch list Items.

Building B:  Complete except for cleaning and correcting punch list items.


Update: (06-01-2018) 

Area A:  Brick is complete except one area where the contractor needed to maintain access.  Storefront framing and glazing is complete.  Ceiling grid is complete.  HVAC Is complete.  Paint primer is complete, Electrical rough-in is complete; light fixtures are installed and powered.  VCT installation has begun.  Area B:  Paint is complete; VCT and base are complete; Casework nearing completion; Ceiling tiles are complete.  Anticipated work to be performed over the next month includes the following:

Area A:  Complete all masonry; complete painting; complete VCT installation.

Area B:  Install marker boards; complete casework installation; clean and wax floors


Update: (05-01-2018) 

Area A:  Brick is nearly complete; Installation of windows has begun; Ceiling Grid is in place in all classrooms; Lighting fixtures are in place in all classrooms.  Area B:  Ceiling Grid is in place; Lighting fixtures are in place; floor prep has begun.  Anticipated work to be performed over the next month includes the following:

2018-05-01.jpg

Area A: Completion of all window installation; Floor prep and start of installation of VCT; Start of final paint

Area B:  Completion of VCT and final paint.


Update: (04-01-2018) 

Area A:  Roofing is in place.  Spray foam insulation has been applied.  Brick work has begun.  Continued installation of MPE rough-in.  Area B:  Ceiling grid is in place; block fill has been applied; installation of windows has begun.  Anticipated work to be performed over the next month includes the following:

2018-04-01.jpg
  •  Area A:  Completion of brick; installation of windows; placement of drywall.
  • Area B:  Completion of window installation; completion of paint; start of VCT installation.

Update: (03-01-2018) 

Area A:  Roofing has begun.  All interior masonry walls are complete; parapet walls are complete; MPE rough-in continues.  Many days of rain have delayed the project, but completion for the start of school is still on schedule.  Area B:  Installation of the face brick is complete.  MPE rough-in continues. Anticipated work to be performed over the next month includes the following:

2018-03-01.jpg
  • Area A:  Completion of the roof; application of spray foam insulation; start of face brick installation. Light gauge metal framing; blocking for windows.
  • Area B:  Block fill; hang and finish drywall; roofing trim-out.

Update: (02-01-2018) 

Area A:  Concrete planks have been placed for the roof.  The topping slab for the second floor has been poured.  Area B:  The spray foam insulation has been applied.  The Roofing has been installed. Placement of face brick continues.  MPE Rough-in continues. Light metal gauge framing continues.  Anticipated work to be performed over the next month includes the following:

2018-02-01.jpg
  • Area A:  Application of waterproofing; Installation of parapet walls; application of spray foam insulation; installation of roof; continuation of MPE rough-in
  • Area B:  Installation of windows; place and start up HVAC equipment; hang and finish drywall; blockfill masonry walls.

Update: (01-01-2018) 

Area A:  Concrete planks are in place for second floor.  Masonry walls at second floor are approximately half complete.  MPE rough-in continues.  Renovations at existing building is underway with demo nearly complete.  Area B:  Spray foam insulation is in place.  Placement of brick has begun.  Framing for interior soffits has begun.  MPE rough-in continues.  Anticipated work to be performed over the next month includes the following:

2018-01-01.jpg
  • Area A:  Continuation of placement of masonry walls; continuation of MPE rough-in.  Wall construction at existing building. 
  • Area B:  Continuation of placement of brick and interior soffits.

Update: (12-01-2017) 

Area B:  Bearing walls are in place and concrete planks are set.  MPE rough-in is proceeding.  Area A:  SOG is in place; load bearing walls are in place.  Anticipated work to be performed over the next month includes the following:

  • Area A:  Concrete planks will be set; load bearing walls for the second floor will be placed; Plumbing and electrical rough-in will continue; waterproofing at exterior walls will be applied.
  • Area B:  Roof will be applied; spray foam insulation at exterior walls will be applied; Brick installation will begin; MPE rough-in will continue.

Update: (11-01-2017) 

Area A:  Stem walls are 100% and have been insulated.  Underslab electrical and plumbing rough-in is complete.  Awaiting electrical inspection.   Area B:  Floor slab is in place and bearing walls are about 90% completed.  Most door frames are set.  Anticipated work to be performed over the next month includes the following

2017-11-01.jpg
  • Area A:  Completion of Radon containment measures; placement of floor slab; erection of bearing walls at least to second floor bearing height.
  • Area B:  Erection of partition walls; erection of structural planks; placement of spray foam insulation.

Update: (10-01-2017) 

At Area B footings are poured and stem walls are being erected.  Electrical rough-in under the slab is ongoing.  At Area A excavation for footings is underway. Anticipated work to be performed over the next month includes the following:

  • Area A:  Pour footings and install underslab plumbing and electrical.
  • Area B:  Complete footings and underslab rough-in.

Update: (09-01-2017)

At Area B footings are being installed.  Where some footings have been installed, masonry walls are being installed.  At Area A, drainage pipe is being installed.  Anticipated work to be performed over the next month includes the following:

2017-09-01.jpg
  • Area A:  Construct footings and begin installation of footings; begin masonry; pour floor slab
  • Area B:  Continue footings and masonry; pour slabs

Update: (08-01-2017)

Demo work of the existing building that was scheduled for summer has been completed.  Anticipated work to be performed over the next month includes the following:

  • Trenching for footings at Area A
  • Construct Temporary Detour walkway at Area B
  • Trenching for footings at Area B