Recently Completed

East Nashville Magnet High School

This project will add new bleachers to the football/track facility.  A new building will also be constructed with concession stand, press box, restrooms, and ticket booth.  A PA system and score board will also be added.  The final component of this project is site work including fencing, sidewalks, and ramps.

East Nashville Magnet High School

Project details

Mayor
Megan Barry
Council
District 5 - Scott Davis email
School board
District 5 - (upon funding) Elissa Kim
(current) Christiane Buggs email
Location
110 Gallatin Avenue map it
Total project square footage
2,896 SF
Allocated funding
$2,750,000
Architect
EOA Architects
Contractor
Romach General Contractors
Anticipated completion date
August 2017

Construction Updates

Updates will be posted on a monthly basis while the project is under construction.


Update: (10/1/2017)

2017-10-01.jpg

Project is substantially complete.


Update: (9/1/2017) 

2017-09-01.jpg

Project will be complete this month.


Update: (8/1/2017)

Visitor’s bleachers concrete pad is in place; irrigation and sod are in place; visitors side micro piles are in place; rip-rap is in place; concession/restroom slab-on-grade is in place; block walls at concession/restrooms is in progress. Anticipated work to be performed over the next month includes the following: 

  • Completion of visitor’s side structure; installation of bleachers
  • Completion of concessions/restrooms walls
  • Installation of trusses and deck. 
  • Installation of new goal posts. 
  • Installation of PA system. 
  • Installation of ramps, stairs and walkways.

Update: (6/1/2017)

The irrigation water line has been installed, the detention pond and associated underground drainage has been installed.  Irrigation piping has begun.  Anticipated work to be performed over the next month includes the following: 

  • Completion of irrigation system
  • Placement of sod
  • Micropile test
  • Installation of concession stand footings

Update: (5/1/2017)

We have obtained a building permit. The contractor has installed erosion control measures and is on site grading preparing for irrigation and sod. Anticipated work to be performed over the next month includes the following:

  • Install underground utilities
  • install segmented retaining walls
  • building visitor’s side bleacher pads

Update: (04/01/2017)

Erosion control has been isntalled.  The project is currently awaiting a grading permit.


Update: (03/01/2017)

Project is under review at the Codes department and awaiting a building permit.


Update: (02/01/2017)

Project is under review at the Codes department and awaiting a building permit.


Update: (01/01/2017)

Project is under review at the Codes department and awaiting a building permit.