Recently Completed

Glencliff High School

This project consists of the construction of a new 400 meter track.  The concession stand and restroom building will also be torn down and constructed a new.  The new building will also include a ticket booth and alumni room.  The final component to this project is sitework including fencing, sidewalks, stairs, and ramps.

Glencliff High School

Project details

Mayor
Megan Barry
Council
District 16 - Mike Freeman email
School board
District 7 - Will Pinkston email
Location
160 Antioch Pike map it
Total project square footage
2,712 SF
Allocated funding
$2,200,000
Architect
Adkisson & Associates Architects
Contractor
Dowdle Construction Group
Anticipated completion date
August 2017

Construction Updates

Updates will be posted on a monthly basis while the project is under construction.


Update: (12-01-2017)

The Track and Stadium work is substantially complete.  The track surfacing will occur in the Spring before track season begins.


Update: (11-01-2017)

The contractor experienced delays due to weather as well as problems installing the perimeter drain near the high jump area.  The contractor has completed the restrooms; completed the painting (both interior and exterior); completed and poured concrete at the perimeter drain.  The running surface for the track cannot be installed until late spring.  Anticipated work to be performed over the next month includes the following:

  • Installation of counter tops
  • sealing of concrete floors
  • installation of vinyl soffit in the areaway between the concession stand and the alumni room
  • placement of asphalt at the track.

Update: (10-01-2017)

The project will be substantially complete by the end of this month.  The track will have asphalt placed; the concession stand and restrooms will be complete and the Alumni room will be complete.


Update: (09-01-2017)

2017-10-01.jpg

The field work is complete.  Work continues on the concession stand and restrooms.


Update: (08-01-2017)

Retaining wall is completed; grading is complete; irrigation is complete; sod had been placed on the field; ramps/stairs are 25% complete.  Anticipated work to be performed over the next month includes the following:

  •  Completion of ramps/stairs
  • Footings/underslab plumbing and electrical at concessions/restroom building
  • Perimeter curb at track
  • Second lift of stone at track
  • Placement of bleachers

Update: (06/01/2017)

Construction Update: (06-01-2017) Underground piping for site drainage is complete.  Site grading is complete except for the West end where the retaining wall is to be constructed.  The concrete pad for the visitor's bleacher is in place.  Anticipated work to be performed over the next month includes the following:

  • Begin work on the retaining wall
  • Complete work on biorentention ponds

Update: (05-01-2017)

Site demo is complete. Site drainage is 75% complete; site grading is 50% complete but unsuitable soils over-excavation and replacement is progress slowly. Anticipated work to be performed over the next month includes the following:

  • Completion of site grading and drainage
  • Installation of grandstand pads
  • Start retaining wall

Update: (04-01-2017)

Demolition is underway and will be completed this month. Anticipated work to be performed over the next month includes the following:

  • Grading will begin.
  • Site drainage work will begin.
  • Relocation of the fiber line between the high school and elementary school will begin.

Update: (03/01/2017)

Project is under review at the Codes department and awaiting a building permit.


Update: (02/01/2017)

Project is under review at the Codes department and awaiting a building permit.


Update: (01/01/2017)

Project is under review at the Codes department and awaiting a building permit.