Recently Completed

Hume-Fogg Magnet High School

This is a complete facility renovation of the existing school. The new design will be in keeping with the design guidelines of the Downtown Historic Commission. The existing hardwood floors and plaster ceilings will be kept intact as much as possible in the new design. Where original windows remain, they will be replaced with new energy efficient windows that are in keeping with the original design aesthetic. This project as includes new lighting, technology infrastructure and new electrical, plumbing and HVAC.

Hume-Fogg Magnet High School

Project details

Mayor
(upon funding) Karl F. Dean
(current) Megan Barry
Council
District 19 - (upon funding) Erica Gilmore
(current) Freddie O'Connell email
School board
District 5 - (upon funding) Elissa Kim
(current) Christiane Buggs email
Location
700 Broadway map it
Total project square footage
201,286 SF
Allocated funding
$23,000,000
Architect
Kline Swinney Associates
Contractor
Messer Construction
Anticipated completion date
December 2017

Construction Updates

Updates will be posted on a monthly basis while the project is under construction.


Update: (5/1/2018)   

The project is substantially complete.  Completed photos will be posted in the coming weeks.


Update: (4/1/2018)   

Phase 7 multipurpose room on the 4th floor finish work is nearly complete.  Hallway renovations are nearly complete.  Phase 7 West Atrium Windows are nearly complete.  Anticipated work to be performed over the next month includes the following:

2018-04-01.jpg

Hume Fogg Renovation Project to be Complete


Update: (3/1/2018)   

Phase 7 multipurpose room on the 4th floor finish work is nearly complete.  Phase 7 staff training room on the 3rd floor finish work is complete.  Hallway renovations are nearly complete.  Anticipated work to be performed over the next month includes the following:

  • Phase 7 Multipurpose Room finish work to be complete.
  • Phase 7 West Atrium Windows to be compete over Spring Break
  • Phase 7 Hallway renovations to be complete

Update: (2/1/2018)   

Phase 7 multipurpose room on the 4th floor finish work is nearly complete.  Phase 7 staff training room on the 3rd floor finish work is complete.  Hallway renovations are nearly complete.  Wrestling Room demolition is complete.  Anticipated work to be performed over the next month includes the following:

  • Phase 7 Multipurpose Room finish work to be complete.
  • Phase 7 Wrestling Room to be compete
  • Phase 7 Hallway renovations to be complete

Update: (1/1/2018)   

Phase 7 multipurpose room on the 4th floor finish work is 95% complete.  Phase 7 staff training room on the 3rd floor finish work is 95% complete.  Hallway renovations are 95% complete.  Wrestling Room demolition is complete.  Anticipated work to be performed over the next month includes the following:

  • Phase 7 Multipurpose Room finish work to be complete.
  • Phase 7 Staff training Room finish work to be complete.
  • Phase 7 Wrestling Room to be compete
  • Phase 7 Hallway renovations to be complete

Update: (12/1/2017)  

Small Gym is complete.  Phase 7 multipurpose room on the 4th floor finish work is nearly complete.  Phase 7 staff training room on the 3rd floor finish work is nearly complete.  Hallway renovations are 90% complete.  Wrestling Room demolition has begun.  Anticipated work to be performed over the next month includes the following:

2017-12-01.jpg
  • Phase 7 Multipurpose Room finish work to be complete.
  • Phase 7 Staff training Room finish work to be complete.
  • Phase 7 Wrestling Room to be compete
  • Phase 7 Hallway renovations to be complete

Update: (11/1/2017)  

Small Gym is nearly complete.  Phase 7 multipurpose room on the 4th floor drywall work is complete.  Phase 7 staff training room on the 3rd floor drywall work is complete.  Exterior Window replacement work is complete.  Hallway renovations are nearly complete.  Wrestling Room demolition has begun.  Anticipated work to be performed over the next month includes the following:

  • Phase 7 Small Gym to be complete.
  • Phase 7 Multipurpose Room finish work to continue.
  • Phase 7 Staff training Room finish work to continue.
  • Phase 7 Wrestling Room to continue.

Update: (10/1/2017)  

Phase 5&6 classrooms are complete.  Phase 7 small gym demolition is complete.  Small Gym painting is 60% complete.  Phase 7 multipurpose room on the 4th floor demolition is complete.  Multipurpose room drywall work is underway.  Phase 7 staff training room on the 3rd floor demolition is complete.  Exterior Window replacement work is 90% complete.  Hallway renovations are 70% complete.  Anticipated work to be performed over the next month includes the following:

2017-10-01.jpg
  • Phase 7 Small Gym finish work to continue.
  • Phase 7 Multipurpose Room rough in work to continue.
  • Phase 7 Staff training Room rough in work to continue.
  • Phase 7 Multipurpose Room finish work to begin.
  • Phase 7 Staff training Room finish work to begin.
  • Phase 7 Wrestling Room to begin.
  • Exterior window replacement to be completed.
  • New Lockers to be completed.

Update: (6/1/2017)  

East Atrium is complete.  Phase 5 classroom demolition is complete.  2nd floor and 3rd floor hallway ceiling clouds are nearly complete.  4th floor hallway ceiling work has begun.  Phase 5 classroom framing is complete.  Phase 5 MPE trim out is underway.  Phase 6 classroom demolition has begun.  Anticipated work to be performed over the next month includes the following:

  • Phase 6 classroom demolition to be complete.
  • Phase 6 Metal Stud Framing to be complete
  • Phase 6 classroom MPE rough in to be complete.
  • Phase 5 classroom finishes to be complete.
  • Hallway ceiling cloud work to continue.
  • Exterior window replacement to begin.

Update: (5/1/2017)

East Atrium smoke evacuation system is complete.   Phase 5 classroom demolition is underway. 2nd floor and 3rd floor hallway ceiling clouds are 60% complete. Anticipated work to be performed over the next month includes the following:

  • Phase 5 classroom demolition to be complete.
  • Phase 5 Metal Stud Framing to be complete
  • Phase 5 classroom MPE rough in to be complete.
  • Phase 5 classroom finishes to begin.
  • Hallway ceiling cloud work to continue.

Update: (4/1/2017)

East Atrium smoke evacuation system is nearly complete. Phase 4 science classroom are complete. Phase 5 demolition is underway. 2nd floor hallway ceiling clouds have begun and are 30% complete. Anticipated work to be performed over the next month includes the following:

  • East Atrium work to be completed.
  • Phase 5 classroom demolition to continue.
  • Phase 5 classroom MPE rough in to begin.
  • Hallway ceiling cloud work to continue.

Update: (3/1/2017)

East Atrium smoke evacuation system is nearly complete. Auditorium sound and lighting are complete. Stage curtains and auditorium seating have been installed. Phase 4 science classroom MEP rough in is complete. Phase 4 finish work is underway. Anticipated work to be performed over the next month includes the following:

  • East Atrium work to be completed.
  • Phase 4 Science rooms to be complete.
  • Phase 5 classroom demolition to begin.
  • Phase 5 classroom MPE rough in to begin.

Update: (2/1/2017)

Mechanical and Electrical trim out, acoustic ceilings and glass railings in the East Atrium are complete. Auditorium sound and lighting are nearly complete. Stage curtain supports have been installed. Phase 4 Science classroom demolition is nearly complete. Phase 4 science classroom MEP rough in is underway. Anticipated work to be performed over the next month includes the following:

2017-02-01.jpg
  • East Atrium work to be completed.
  • MPE rough in for Phase 4 Classrooms to continue
  • Auditorium to be completed and turned over.

Update: (1/1/2017)

East Atrium Mechanical and Electrical trim out is underway. Phase 3 stack restrooms are complete and have been turned over to the school. Phase 3 classrooms have been completed. East Atrium finish work to continue. Auditorium Demolition work has begun.  Anticipated work to be performed over the next month includes the following:

  • East Atrium work to continue.
  • Demolition of Phase 4 Science room to begin
  • MPE rough in for Phase 4 Classrooms to begin
  • Auditorium Sound and Lighting rough in to begin

Update: (12/1/2016)

East Atrium Mechanical and Electrical rough in is complete. Phase 3 stack restrooms are complete. MPE trim out for 3rd Floor Classrooms are underway. Acoustical ceilings are completed for Phase 3 classrooms. East Atrium finish work to continue. Anticipated work to be performed over the next month includes the following:

2016-12-01.jpg
  • Flooring for Phase 3 Classrooms to be completed
  • MPE trim out for Phase 3 Classrooms to be completed
  • Phase 3 Classrooms and Restrooms to be turned over.
  • Phase 4 Classroom Demolition to begin.

Update: (11/1/2016)

East Atrium Mechanical and Electrical rough in is in progress. Drywall hanging and finishing for Phase 3 stack restrooms is 60% complete. Tile Floors for Phase 3 stack restrooms are 80% complete. Demolition of 3rd Floor Classrooms are complete. Anticipated work to be performed over the next month includes the following:

  • Phase 3 restroom tile work to be completed
  • Demolition of 3rd floor for Phase 3 to continue.
  • MPE rough in for Phase 3 Classroom to be completed
  • MPE trim out for Phase 3 restrooms to be completed

Update: (10/1/2016)

Steel work for East Atrium is Complete. East Atrium Mechanical and Electrical rough in is in progress. Metal stud framing and MPE Rough-in for Phase 3 stack restrooms is complete. Art Room is complete. Anticipated work to be performed over the next month includes the following:

  • Phase 3 restroom drywall to begin
  • Demolition of old Art room to begin.
  • Demolition of 3rd floor for Phase 3 to continue.
  • MPE Rough-in for Phase 3 Classroom to begin

Update: (9/1/2016)

Steel work for East Atrium is ongoing. Slope Glazing at Art room is completed. East Atrium Mechanical and Electrical rough in is in progress. Test and Balance of Phase 2 HVAC units is in progress. Phase 2 outside air units have been installed. Demolition of 1st floor hallway ceiling for Phase 3 has begun. Anticipated work to be performed over the next month includes the following:

  • Phase 3 restroom Mechanical and Electrical rough in to continue
  • Art room to be completed by the end of the month.
  • Demolition of old Art room to begin.
  • Demolition of 3rd floor for Phase 3 to begin.

Update: (8/1/2016)

Kitchen and Cafeteria work is complete. Phase 2 Administration and Library work is complete. Steel work for East Atrium is ongoing. Slope Glazing at Art room is completed. Anticipated work to be performed over the next month includes the following:

  • Test and Balance of new fan coil units for Phase 2.
  • Phase 3 restroom stack demolition to begin
  • Art room to be completed by the end of the month.
  • Installation of Phase 2 Outside Air units to be completed.

Update: (7/1/2016)

Drywall for Phase 2 is complete. Painting and trim is nearly complete. Ceiling grid and floor tile is complete. Demolition of Kitchen and Cafeteria Work is complete. Under slab rough in for Kitchen is completed and slab has been re-poured. Carpet for Administration area has been installed. Steel work for East Atrium is nearly complete. Anticipated work to be performed over the next month includes the following:

  • Ceiling tile installation for clouds.
  • Slope Glazing at Art room.
  • Kitchen and Cafeteria completion.

Update: (6/1/2016)

Finishing of drywall for Phase 2 is nearly complete. Painting of walls and trim is underway. Overhead rough in for Phase 2 is complete. Structural steel for new openings in existing masonry walls is complete. Tile flooring in bathrooms is in progress. Demolition of Kitchen and Cafeteria Work has begun. Anticipated work to be performed over the next month includes the following:

  • Installation of new fan coil units.
  • Ceiling grid installation for clouds.
  • Flooring installation.
  • Kitchen and Cafeteria work.

Update: (5/1/2016)

Wall Framing on the second floor is complete. Wall rough in for Phase 2 is complete. Hanging and finishing of drywall work continues. Overhead rough in for Phase 2 is underway. Structural steel for new openings in existing masonry walls are complete. Anticipated work to be performed over the next month includes the following:

  • Finishing of drywall for Phase 2.
  • Continuation of overhead rough in for Phase 2.
  • Installation of wood base.
  • Coordination of Kitchen and Cafeteria Renovation for Summer work.

Update: (3/1/2016)

Wall Framing on the second floor is ongoing. Roughing in Phase 2 restrooms is ongoing. Demolition work is being performed in preparation for summer work. Anticipated work to be performed over the next month includes the following:

  • Continuation of framing and rough in of new walls.
  • Commencement of installation of structural steel for new openings in existing masonry walls Phase 2.
  • Framing MPE rough in of new restrooms.

Update: (2/01/2016)

Demolition for phase 2 is underway. New construction for phase 2 will begin this month. Anticipated work to be performed over the next month includes the following:

  • Commence rough-in of Mechanical, Plumbing and Electrical.
  • Rough trades, carpentry, blocking, framing.
  • Ordering of finish materials for all of Phase 2.

Update: (1/01/2016)

Demolition is ongoing in Phase 2. Installation of infrastructure (sleeves and cabling) for telecommunications items for all phases is ongoing.   Anticipated work to be performed over the next month includes the following:

  • Completion of demolition of phase 2 areas.
  • Issue contracts by Construction Manager for sub contracts all disciplines in Phase 2.
  • Completion of the furniture design

Update: (12/01/2015)

Demolition has commenced and is about nearing completion. Construction will begin soon on the phase 2 areas of renovation. Anticipated work to be performed over the next month includes the following:

  • Demolition of phase 2 areas.
  • Demo of conduit and raceways not remaining as part of the new construction
  • Bidding by the Construction Manager for sub contracts all disciplines in Phase 2.
  • Awarding of sub-contracts to successful bidders.
  • Preparation and commencement of finishes as applicable.