Recently Completed

Rosebank Elementary School

This project is a complete facility renovation. The building will be modernized and receive new windows, HVAC system, and lighting. The cafeteria will be expanded along with the kitchen. The library will be expanded and modernized, as well.

Rosebank Elementary School

Project details

Mayor
(upon funding) Karl F. Dean
(current) Megan Barry
Council
District 06 - (upon funding) Peter Westerholm
(current) Brett Withers email
School board
District 05 - (upon funding) Elissa Kim
(current) Christiane Buggs email
Location
1012 Preston Drive map it
Total project square footage
65,898 SF
Allocated funding
$6,000,000
Architect
Centric Architecture
Contractor
Carden Company
Anticipated completion date
January 2018

Completed Photographs

Professional Photos Coming Soon

2018-01-01f.JPG
2018-01-01h.JPG
2018-01-01g.JPG

Update: (01/01/2018)

The renovation of Rosebank Elementary is substantially complete.  Completed project photos to be posted soon.


Update: (12/01//2017)

Phase 3: The final 10 classrooms are almost complete. They should be ready for release after Winter Break and this will complete our renovation of Rosebank Elementary School. Anticipated work to be performed over the next month includes the following:

  • Final calibration of projectors and equipment
  • Commissioning on mechanical equipment
  • Punch List items and touch up
  • Documentation for LEED certification
  • Cleaning and re-grouting of serving line in cafeteria
  • Sound assessment on Cafeteria

Update: (10/01//2017)

Phase 3:10 classroom wing continues final demolition and begins finish work. Anticipated work to be performed over the next month includes the following:

2017-10-01.jpg
  • Painting
  • Plumbing and electrical rough-ins
  • Review and order of new mechanical equipment
  • Light installation

Update: (09/01//2017)

Phase 3:10 classroom wing continues demolition. Anticipated work to be performed over the next month includes the following:

2017-09-01.jpg
  • Demolition of plumbing, electrical, and mechanical
  • Plumbing and electrical rough-ins
  • Review and order of new mechanical equipment

Update: (08/01//2017)

Phase 2 Classrooms are complete. Teachers and students are moved in. Kitchen and Cafeteria area complete. Meals are being served and students are enjoying their new bright eating space. Construction is now transitioning over to Phase 3: 10 classroom wing. Anticipated work to be performed over the next month includes the following:

2017-08-01.JPG
  • Demolition of finishes
  • Movement of surplus furniture

Update: (07/01//2017) Phase 2 classrooms are now receiving final paint. Ceiling grid has been dropped. All data and alarm wiring is complete. New windows are being installed and other finish work. Phase 3 (Alternates 1 and 2) were approved by the board and will now be added to the contractor’s official scope of work. Anticipated work to be performed over the next month includes the following:

2017-07-01.jpg
  • Kitchen/Cafeteria tiling, painting, VCT flooring
  • Kitchen equipment installation
  • Classroom painting, lights and diffusers, VCT flooring, Acoustic ceiling tile
  • Outdoor pathways to Pre-K playground

Update: (06/01//2017)

Phase 2 continues with finish work, wiring, masonry, and fire sprinkler. Demolition of the kitchen and cafeteria is near completion. Construction is heavy on kitchen and cafeteria. Anticipated work to be performed over the next month includes the following:

  • Kitchen/Cafeteria demolition
  • Kitchen/Cafeteria mechanical, plumbing, and electrical rough-in
  • Kitchen/Cafeteria roofing repairs
  • Electrical wiring in classrooms
  • Drywall finishing in classrooms
  • Masonry patching
  • Fire sprinkler installation 

Update: (05/01//2017)

Demolition of phase 2 classrooms continues with mechanical, plumbing and electrical rough-ins. Finish work is beginning. Anticipated work to be performed over the next month includes the following:

  • Demolition of boiler room
  • Mechanical, Plumbing, and Electrical rough-ins
  • Metal stud framing
  • Concrete slab patching
  • Sprinkler piping
  • Miscellaneous masonry work

Update: (4-01-2017)

Phase 2 transition continues. Demolition of stage in cafeteria is complete. Demolition of phase 2 classrooms continues with mechanical, plumbing and electrical rough-ins. Anticipated work to be performed over the next month includes the following:

  • Salvaging of materials
  • Demolition of Phase 2 classrooms and equipment in boiler room
  • MP&E rough-ins
  • Concrete slab patching

Update: (3-01-2017)

Construction on Phase 1 is complete! Teachers and students are moving in and settling in their new classrooms. Construction of Phase 2 will occupy the first and second floors of the old building, excluding the 3rdand 4th grade wing. Anticipated work to be performed over the next month includes the following:

  • Transitioning to Phase 2
  • Salvaging of materials
  • Asbestos Abatement
  • Demolition

Update: (2-01-2017)

 Installation of new storefront windows is complete. Ceiling tiles are being installed in both wings. VCT and final floor coverings are being installed with walls being touched up. Everything is on schedule for Substantial Completion of Phase A on February 13. Anticipated work to be performed over the next month includes the following:

  • Window shade installation
  • Fire Alarm switch over
  • Finish flooring and base installation
  • Testing and Balancing

Update: (1-01-2017)

 Installation of new storefront windows is finishing. Ceiling grid is installed in the new admin area and STEM wing. Final colors are being painted in the Phase 1 spaces. Lockers are installed in the classrooms. Anticipated work to be performed over the next month includes the following:

  • Completion of window replacement
  • Ceiling tile, VCT & Carpet, Casework installation
  • Fire alarm replacemen and Fire and domestic service lines installation outside gym
  • New grease trap line installation outside cafeteria
  • Sidewalk replacement at main entrance

Update: (12-01-2016)

Installation of new storefront windows has begun. Ceiling grid is being installed in the new admin area along with casework and other finishes. The STEM wing is being painted. The Pre-K wing is finishing up above ceiling rough-ins and drywall finishing. Anticipated work to be performed over the next month includes the following:

  • Window Replacement in the new Admin Area
  • VCT & Carpet installation
  • Fire alarm replacement
  • Doors & hardware

Update: (11-01-2016)

Drywall finishing continues in the new Admin area along with above ceiling rough ins. The STEM wing is now receiving metal studs and drywall finishing with above ceiling rough-ins as well. Framing, electrical, and plumbing rough-ins are complete in the Pre-K and K wing.  Anticipated work to be performed over the next month includes the following:

  • Window Replacement in the new Admin Area
  • Plumbing, HVAC, and Electrical rough-ins in STEM and Administrative suite
  • Finishing in STEM, Pre-K/K wing, and Administrative suite
  • Site utility work and sidewalk repair

Update: (10-01-2016)

The gym lobby opened just after fall break. Metal stud framing continues in the new Admin area along with drywall finishing and above ceiling rough ins. The STEM wing is receiving plumbing, electrical and HVAC rough ins as well as sprinkler piping. Underslab utility work is continuing in the Pre-K wing.  Anticipated work to be performed over the next month includes the following:

  • Plumbing, HVAC, and Electrical upgrades in STEM and Administrative suite
  • Finishing in Administrative suite
  • Slab patching at Pre-K wing
  • Site utility work and Sidewalk repair

Update: (9-01-2016)

New ducts are being hung in new administrative suite and classrooms. Drywall is being hung in administration. Connections for new sanitary pipes are under construction. Demolition continues in new STEM wing. Anticipated work to be performed over the next month includes the following:

  • Completion of Gym Lobby
  • Completion of Conference Room
  • Plumbing, HVAC, and Electrical upgrades in STEM and Administrative suite
  • Finishing in Administrative suite

Update: (8-01-2016)

Interior abatement is complete for the first phase. New VCT is laid in the playroom and the new cafeteria wall is built. Framing has begun on the new administration suite and demolition continues in the new STEM wing. Anticipated work to be performed over the next month includes the following:

  • Start up and commissioning of the new HVAC unit in playroom
  • Construction of temporary walls and partitions
  • Construction of new Administration suite
  • Additional demolition of classroom spaces

Update: (7-01-2016)

Interior abatement is still in progress and nearly complete. Demolition has begun on the critical summer work including: playroom and playroom lobby as well as cafeteria. Anticipated work to be performed over the next month includes the following:

  • Construction of cafeteria cut-through pathway
  • Construction of new storage and riser rooms off of playroom
  • Portable classroom relocation and commissioning
  • Installation and commissioning of new HVAC in playroom

Update: (6-01-2016)

Awarded contractor has been issued a Notice to Proceed. Interior abatement is in progress and scheduled for completion this month. Anticipated work to be performed over the next month includes the following:

  • Contractor mobilization
  • Material and equipment ordering
  • Demolition